LNA has the capacity to deliver a full range of services required in the different stages of a mining project, from preliminary evaluations to equipment acquisition, construction project management and commissioning, encompassing a wide range of commodities including iron ore, gold or cement.
We have provided services to some of the major north american mining companies like Goldcorp, Agnico Eagle, Suncor, Consolidated Thompson, Nemaska Lithium, McInnis Cement and others.
During its long history and significantly in recent years LNA has been involved in the development of well known projects and installations, developing and extending its management capacity and evolving very significantly in the following sectors:
2009-2010
Bloom Lake, Québec
The Bloom Lake Project is the first major iron ore project in Eastern Canada since the 1970s.
During the Phase 1, LNA was required to manage all site construction activities for the construction of an iron ore processing plant with a capacity of 8 million tonnes of concentrate.
A team of engineers and technicians were mobilized on-site to launch our Quick Project Recovery Task Force (QPRTF) procedure and provide the Construction Management and Project Control for the entire site, from the gyratory crusher up to the concentrated storage and load-out facilities including the tailings infrastructure and all related services.
Contract development and preparation for Civil, structural, mechanical & piping construction works.
Responsible for the planning, contract preparation, tender analysis, negotiations and recommendations, field supervision and verification of all contract changes and approval
Start-up
Implication of the constructability for the phases of execution.
LNA used innovative management techniques to meet project fast-track schedule.
2009-2010
Bloom Lake, Québec
Under the Phase 1 of the Consolidated Thompson project, a complete port infrastructure was required for receiving and loading the processing plant concentrate: Port installation, railway, load-out station, stacker /reclaimer, conveyor system and ship loader.
2011-2013
Bloom Lake, Québec
During the Phase 2 of the Cliffs Natural Resources project (after the acquisition of Consolidated Thompson), LNA was required to manage all the construction activities of an additional 8 million tonnes iron ore processing plant to increase the production capacity of existing facilities.
LNA was in charge of the Construction Management and Project Control of the entire site, from Crushing Facility to car loading station including civil, concrete, structural, electrical, mechanical & piping construction works.
Responsible for the planning, contract preparation, tender analysis, negotiations and recommendations, field supervision and verification of all contract changes and approval.
Preparation of cost estimates and budget reviews.
Implication of the constructability for the phases of execution.
Mobilization of a team of engineers and technicians on-site.
2015-2017
Port Daniel-Gascons, Québec
McInnis cement plant, producing more than two millions tonnes of cement annually, is one of largest industrial projects recently built in eastern North America.