During the Phase 2 of the Cliffs Natural Resources project (after the acquisition of Consolidated Thompson), LNA was required to manage all the construction activities of an additional 8 million tonnes iron ore processing plant to increase the production capacity of existing facilities.
LNA was in charge of the Construction Management and Project Control of the entire site, from Crushing Facility to car loading station including civil, concrete, structural, electrical, mechanical & piping construction works.
Responsible for the planning, contract preparation, tender analysis, negotiations and recommendations, field supervision and verification of all contract changes and approval.
Preparation of cost estimates and budget reviews.
Implication of the constructability for the phases of execution.
Mobilization of a team of engineers and technicians on-site.
COMMISSIONING COMPLETED FOR:
- Primary gyratory crusher
- 3.8 km Over land conveyor
- Dust collector system
- A 315 kV electrical sub-station
- Tailing Booster Pump Station
- Processed Water Pumping Station